What belongs in a commercial rendering quotation?
Compare measured work, investigation allowances, access and programme assumptions before comparing the tender totals.

A commercial rendering price is useful when its scope can be checked against the building. The quotation should make clear what is included now, what depends on investigation and what another trade must complete first. This guide sets out the items to reconcile across bids.
Issue one measured description to every bidder
Use elevation references that remain consistent between the drawings, survey and pricing schedule. State the drawing revision and identify any areas outside the contract. Ask how openings, reveals, returns and small isolated surfaces have been measured. A bidder who has allowed for the front and both returns is pricing a different package from one who has measured only the broad face.
Put provisional dimensions in a separate column and say who will confirm them. If the drawings change during tender, issue the change to everyone with a clear response date. Keep the original and revised quantities so the effect on the price is visible. This is especially useful where a window arrangement or retained brick panel changes late in design.
Identify the work hidden inside preparation
Preparation may include investigations, removal, substrate repairs and treatment of interfaces. Ask for the expected extent and the assumptions behind it. Where the surface condition is unknown, define the investigation first and the approval point for any extra work. A provisional allowance should describe the uncertainty it covers, rather than conceal an undefined preparation obligation.
Separate work on the render from repairs to adjacent fittings. If a downpipe must be removed, a sign relocated or a window detail changed, establish which package pays for and carries out the task. Include reinstatement in the comparison. An attractive finish price can still leave the client arranging several necessary pieces of work separately.
Scroll sideways to see the full table. Keyboard: focus the table, then use the arrow keys.
| Item | Clarify before accepting |
|---|---|
| Measured render area | Elevation references, openings and returns |
| Investigation | Method, extent and resulting report |
| Preparation | Removal and substrate repair assumptions |
| System | Named construction and specification revision |
| Access | Equipment, duration and restrictions |
| Interfaces | Work by other trades and reinstatement |
| Changes | Instruction and valuation process |
| Handover | Inspection and maintenance records |
Price the actual access arrangement
Ask whether the proposal assumes uninterrupted possession of the working area or repeated visits around the occupier. Compare scaffold duration, delivery arrangements and any need to move protection between phases. Where the client supplies access, state what will be available and when. The bidder should identify any additional requirement rather than assume the platform suits every operation.
HSE identifies boundaries, neighbouring uses and access as information the client should provide for public protection. In pricing terms, record the agreed arrangement and who supplies each part of it. If a public route or another occupier is affected, establish the necessary permissions and coordination before the programme relies on that space.

Keep finish choices and variations traceable
Identify the accepted sample and its relationship to the specification. A colour or texture change may affect procurement, junctions or the planned sequence, so ask for the consequences before issuing the change. Keep the decision with the drawing and product records. The same applies when the specified product becomes unavailable: an alternative needs a technical decision as well as a revised price.
Agree how discoveries will be photographed, described and authorised. A written variation should identify the affected area and the work being added or omitted. Keep separate decisions separate; a repair discovered during removal and a later preference for a different colour are not the same reason for a change.
Read the programme and commercial terms together
Check the assumptions behind the start date, completion stages and access removal. Allow time for outstanding design decisions and any required approvals. Confirm the contracting business, payment provisions, treatment of delay and the process for resolving disputed work in the actual written agreement.
For a quotation discussion, call 01925 918785 with the location, building use and available scope documents. Say which decisions are already fixed and which remain open. That makes it possible to discuss the next information required without presenting an early allowance as a confirmed project price.